I am having some trouble here acounting for how much time the agents have worked. For example the following output.
The agent worked from 9AM to 6PM she logged out during lunch (1 hour).
But i get this in the report?
- Code: Select all
---------- AGENT TIME SHEET: 807 - XXXXXXXXX -------------
TOTAL CALLS TAKEN: 154
TALK TIME: 4:42:00 AVERAGE: 1:50
PAUSE TIME: 0:32:24 AVERAGE: 0:13
WAIT TIME: 3:00:36 AVERAGE: 1:10
WRAPUP TIME: 0:57:36 AVERAGE: 0:22
----------------------------------------------------------------
TOTAL ACTIVE AGENT TIME: 9:12:00
FIRST LOGIN: 2008-01-31 09:01:40
LAST LOG ACTIVITY: 2008-01-31 17:57:54
-----------------------------------------
TOTAL LOGGED-IN TIME: 8:56:24
How can she have almost 9:12 hours when she could only add as much as 8 hours if she worked the whole time?
Any ideas what i might have misconfigured?
Greetings,
Alejandro